Closure of M20 between Junctions 4 and 6 at Aylesford. – New date.

When:
9th November 2018 @ 10:00 pm – 12th November 2018 @ 5:00 am
2018-11-09T22:00:00+00:00
2018-11-12T05:00:00+00:00
Where:
Teapot Lane,
Teapot Ln
Aylesford ME20 7JU
UK

A complete closure of the M20 between Hollingbourne and London at Junctions 4 to 6 for the construction of a new Teapot Lane Footbridge over the M20. Diversions will be in place.

This closure for demolition was originally scheduled for 27th to 30th July 2018 but was postponed to 14th to 17th September because of the hot weather in July. This new work should finish the project.

Pictured below is the former Teapot Lane Footbridge over the M20.