M20 Contraflow Scheme will take two weeks to activate (with traffic problems for Hollingbourne).

The M20 between Junction 8 in Hollingbourne and Junction 9 in Ashford is to be used as lorry park for up to three thousand trucks awaiting passage at Dover in the event of delays caused by industrial action or the lack of a seamless customs arrangement after Brexit which seems likely at the time of writing. The coast bound side is to be used for parking while the London bound side is to be turned into a contraflow arrangement by using the hard shoulder as an extra lane. Highways England have already said that the conversion work will take months and lead to traffic delays. The project is called Operation Brock.

Today KM Online is reporting that once there is a requirement to use the contraflow is established that it will take two weeks to activate it which is likely to mean two weeks of Operation Stack when large parts of Kent will be brought to a standstill including possibly Hollingbourne as happened in 2015. For more information please go to http://www.kentonline.co.uk/kent/news/stack-solution-could-take-two-weeks-to-deploy-185765/

The text of the report is as follows:-

Interim Operation Stack solution could take weeks to deploy

By Paul Francis
00:01, 05 July 2018
Plans for a contra-flow along the M20 as an interim solution for Operation Stack could take two weeks to deploy, it has emerged.

Highways England has confirmed that among the options under consideration for a contraflow is one that could involve a moveable barrier – but that it could take up to a fortnight to set out whenever it is needed.

And in other unwelcome news, Kent County Council says the interim plans are “not sufficiently advanced” to be ready in time for Brexit next year and a permanent lorry park is unlikely to be built before 2023.

Kent County Council transport chiefs have warned the new version of Operation Stack – dubbed Operation Brock – could cause “massive disruption.”

The contingency plan was set out by ministers in May alongside a wider consultation on a permanent lorry park.

Highways England said in a statement: “We are developing a design for the temporary solution and have asked our suppliers to provide a design that can be deployed within two weeks.

“We will work to minimise the impact to road users during this deployment, this includes minimising road closures where this can be done without compromising safety.”

“The solution will involve a contraflow system with traffic using the London-bound carriageway with slow moving freight traffic using coast bound, between junctions 8 and 9.

“The solution is currently in the development stage. We will provide more detail when designs are finalised towards the end of the year.”

The agency stressed that several options were being examined.

ut Kent County Council officials have told MPs the contra-flow has the potential to risk “massive disruption” to both local and strategic traffic.

The warning comes in a submission by the council to the cross-party transport select committee, which is carrying out an inquiry into the impact of Brexit on the freight industry.

KCC said in evidence to the committee there was a risk the new solution could prove just as disruptive as the current arrangements:

“Any plan to hold HGVs on the M20 while also allowing non-port traffic to continue to travel in both directions will significantly reduce capacity on the M20 with a contraflow on the London-bound carriageway for non-port traffic between Junctions 8 and 9, and the likelihood of a 50mph speed restrictions.

“This may result in the kind of massive disruption to both strategic and local traffic that is suffered with the existing arrangements for Operation Stack.”

Cllr Mike Whiting (Con), KCC cabinet member for transport, said: “The government has not yet set out fully what it wants; there does appear to be a lack of detail and we have some serious concerns about the proposals.”

KCC has also highlighted to MPs that it could take years to build a lorry park as a permanent solution to Operation Stack, saying: “We are disappointed the completion date of any such scheme, if it is taken through the Development Consent Order (DCO) process, is now likely to be 2023 at the earliest, eight years after the Government’s commitment in the Autumn Statement of 2015 to deliver a solution ‘at pace’”.

The potential setbacks are underlined in a separate report due to be considered by county councillors next week.

It says: “KCC is also concerned that Highways England’s plans for the temporary solution to Operation Stack do not appear to be far enough advanced to be ready in time for the UK’s exit from the EU.

“It is essential that a solution is in place that enables the M20 motorway to remain open in both directions with sufficient capacity to allow effective flow on the Strategic Road Network and maintain freight fluidity through the Channel ports.”

Pictured below: (Top) is the M20 in Hollingbourne in June 2015 when Operation Stack went on for over 30 days. At the time the London bound side was partially used for storing vehicles. With Operation Brock it is intended that it will be used for vehicles going in both directions with a 50 mph limit. (Bottom) is traffic jam in Eyhorne Street in July 2015 caused by Operation Stack.

Operation Stack at Hollingbourne in June 2015.
The queue in Eyhorne Street one morning in July 2015 when congestion around Junction 8 of the M20 was caused by Operation Stack.