Update on M20 Smart Motorway Project.

Hollingbourne Parish Council has received the following update from Kier on the M20 Smart Motorway Project. Please read more for further information.

Please see below and attached the weekly update for the M20 Smart Motorway Project.

You are receiving this email because we would like to send you regular updates about the M20 Junctions 3 to 5 Smart Motorway work programme. If you wish to unsubscribe, please contact me at the email address below and you will be removed from the list. You can re-join at any time upon request.
 

Weekly Update on SMP M20 Programmed Work
Works Information
Monday 28 January – 01 February 2019

Work to reduce congestion and improve journey times continues this week with narrow lanes and a reduced speed limit of 50mph both east and westbound 24/7.  Free recovery service and speed enforcement are in place to ensure drivers and road workers safety.

Monday 28 January – 01 February 2019 (Inclusive)
Full closure of the westbound M20 junction 5 entry slip road and lanes 1 & 2 closures on the westbound main carriageway, overnight only between 20:00 and 06:00hrs.

In addition to this we will have an overnight lane closure on the merge from the M26 to the M20 eastbound, and a lane one closure on the M20 junction 5 exit slip eastbound.

For further information contact:
Tracey Arnold, Stakeholder and Customer Liaison Manager at tracey.arnold@kier.co.uk or M20.J3-5Smart@highwaysengland.co.uk or sign up for updates at  https://highwaysengland.co.uk/projects/m20-junctions-3-to-5-smart-motorway/

Please let me know if you have any questions.

Many thanks

Tracey Arnold
Stakeholder, Communications and Customer Liaison Manager

M20 SMART MOTORWAYS PROGRAMME